Meta's planned 5-gigawatt Hyperion campus in Louisiana would use 43.8 terawatt-hours a year running flat out, more than every major city we compared except New York. The City Line-Up ranks eight gigawatt-scale AI campuses against the cities they now rival.

Updated Nov 12, 20266 charts · 4 key stats18 primary sources
Fig. 1

The City Line-Up

Annual electricity use of 13 U.S. cities (gray rungs, TWh, log scale) and what eight gigawatt-scale AI data center campuses would use running at full power all year (dashed blue rungs), with the rank each campus would take among the cities.

U.S. cities vs. AI data center campusesAnnual electricity use · TWh5102050New York City 50.1 TWhHyperion (5 GW): 43.8 TWh → #2San Antonio 25.9 TWhAmazon IN (2.4 GW): 21 TWh → #3Los Angeles 20.7 TWhFairwater (2 GW): 17.5 TWh → #4Phoenix 17.5 TWhSusquehanna (1.92 GW): 16.8 TWh → #5Austin 14.6 TWhMemphis 13.7 TWhPhiladelphia 13.1 TWhJacksonville 13 TWhNashville 12.3 TWhFrontier (1.4 GW): 12.3 TWh → #10Stargate WI (1.3 GW): 11.4 TWh → #10Stargate TX (1.2 GW): 10.5 TWh → #10Sacramento 10.5 TWhSeattle 9.1 TWhPrometheus (1 GW): 8.8 TWh → #12New Orleans 5.6 TWhMadison, Wis. 3.2 TWh

Campus values are derived: planned capacity × 8,760 hours. Real campuses run below full power (LBNL estimates about 50% average use of interconnection capacity), so treat them as ceilings. City figures differ in definition and year: New York City is NYISO Zone J grid load (2025); Philadelphia and Phoenix are citywide use from city inventories (2022); the rest are 2025 retail sales of the utility serving each city, whose territory can extend past city limits.

Meta Hyperion at full power, per year
43.8 TWh
5 GW × 8,760 hours; 87% of New York City's 2025 load (derived)
SourcesMeta1; NYISO9
Homes' worth of power in 1 GW, all year
~812,000
8.76 TWh ÷ 10,791 kWh per U.S. home (2022), derived
SourceEIA (FAQ)13
U.S. data center electricity use, 2024
192 TWh
4.7% of U.S. electricity; 649 TWh projected for 2030
SourceLBNL14
Large loads seeking to connect to Texas's grid
474 GW
As of June 2026; ~90% are data centers (ERCOT)
SourceERCOT15
Fig. 2

Meta's Hyperion is twice the size of any other planned AI campus

Largest AI data centers by planned power capacity, gigawatts, as stated by the developer or its utility.

Meta Hyperion5 GWAmazon Indiana2.4 GWMicrosoft Fairwater2 GWAmazon Susquehanna1.92 GWVantage Frontier1.4 GWStargate Wisconsin1.3 GWStargate Abilene1.2 GWMeta Prometheus1 GW+

Stargate Wisconsin is the Vantage / OpenAI / Oracle site at Port Washington. Developers measure capacity differently: Meta says "compute capacity", Crusoe "total power capacity", Vantage Frontier "GPU compute capacity". Susquehanna is the power Talen will deliver to Amazon under contract, and Port Washington is WEC Energy's demand forecast through 2030 (Vantage itself says "close to a gigawatt" of AI capacity). Most campuses are still being built.

Fig. 3

At full power, Hyperion would use more electricity than 19 states

Data center electricity use vs. state electricity use: Hyperion at full power vs. 2025 retail sales of the states nearest in size, TWh

Mississippi49.5 TWhHyperion, full power43.8 TWhKansas41.5 TWhNevada39.8 TWhNebraska37.6 TWhUtah35.3 TWhWest Virginia33.7 TWhNew Mexico31.5 TWhNorth Dakota30.3 TWhConnecticut27.7 TWhIdaho26.8 TWh

Hyperion is 5 GW × 8,760 hours (derived). Below Idaho, the states it would also exceed are Wyoming, Montana, South Dakota, Delaware, Maine, New Hampshire, Hawaii, Rhode Island, Alaska and Vermont (5.5 TWh), plus the District of Columbia. State values are all-sector retail sales.

Fig. 4

Even at half power, Hyperion would out-use Los Angeles

Hyperion's annual electricity use at full power and at 50% average use vs. Los Angeles and Phoenix, TWh

Hyperion, full power43.8 TWhHyperion, 50% use21.9 TWhLos Angeles (LADWP)20.7 TWhPhoenix17.5 TWh

LBNL estimates that U.S. data centers use about 50% of their grid interconnection capacity on average, "due to high redundancy requirements and maintenance needs." Both Hyperion values are derived; Meta does not publish expected annual use. Los Angeles is 2025 retail sales; Phoenix is 2022 citywide use.

Fig. 5

Amazon has contracted 77% of a nuclear plant's capacity

Susquehanna nuclear plant (Pa.) generating capacity, megawatts: power contracted to Amazon's data center campus vs. the rest

77.0%23.0%
  • Contracted to Amazon1,920 MW77.0%
  • Rest of the plant574 MW23.0%
  • Susquehanna generating capacity2,494 MW100%

Talen will supply 1,920 MW to Amazon through 2042, ramping to full volume no later than 2032. Plant capacity (2,494 MW) is from Talen's 2025 10-K; Talen owns 90% of the plant. "Rest of the plant" and the 77% share are derived. Running all year, 1,920 MW is 16.8 TWh, more than Philadelphia's 13.1 TWh in 2022.

Fig. 6

U.S. data centers could use more power than Texas by 2030

U.S. data center electricity use, TWh: 2024 estimate and LBNL Reference Case forecasts

0175350525700202420282030Texas retail sales, 2025: 533 TWh649 TWh192 TWh

2024 is LBNL's last historical year; 2028 and 2030 are Reference Case forecasts (2030 range: 521–843 TWh). LBNL publishes no values in between, so the lines are straight segments. Excludes cryptocurrency mining. Texas is EIA 2025 retail sales, the largest of any state.

Free to republish

Add This Graphic to Your Website

Paste one snippet and every chart, stat and citation above appears on your page. It stays interactive and responsive, and it updates automatically when we revise the data.

  • All sources travel with every card
  • Resizes to fit any column width
  • Light or dark theme, full set or a single card
  • Free with attribution, which is built in
Share this graphic
<div class="graphic-embed" data-graphic="ai-data-center-power-consumption">
  <a href="https://hardware.co/graphics/ai-data-center-power-consumption">AI Data Center Power Consumption vs. Cities (2026)</a> by hardware.co
</div>
<script async src="https://hardware.co/embed.js"></script>
Auto-resizes to fit its content. Works on WordPress, Webflow, Squarespace, Ghost and plain HTML.
Preview

How much power does an AI data center use?

The largest AI data centers now being built are planned at 1 to 5 gigawatts each, and a 1 GW campus running flat out for a year would use 8.76 terawatt-hours (TWh) of electricity. Meta's Hyperion campus in Richland Parish, Louisiana, which Meta expanded in July 2026 "to 5 GW in compute capacity," would use 43.8 TWh a year at full power. That is 87% of the 50.1 TWh New York City drew from the grid in 2025, according to NYISO.

These are ceilings, not forecasts. Developers announce capacity, not expected consumption, and data centers rarely run at full draw. Lawrence Berkeley National Laboratory (LBNL) estimates that U.S. data centers use about 50% of their grid interconnection capacity on average. At that rate Hyperion would still use about 21.9 TWh a year, slightly more than Los Angeles's utility sold in 2025 (20.7 TWh).

What are the largest AI data centers?

Meta's Hyperion, at 5 GW, is the largest AI data center campus with a published capacity, more than twice the next largest. Amazon plans 2.4 GW of data center capacity in Northern Indiana, Microsoft says its Fairwater campus in Wisconsin will scale to 2 GW, and Talen Energy will deliver 1,920 megawatts from its Susquehanna nuclear plant to an Amazon campus next door. Vantage's Frontier campus in Texas (1.4 GW), the OpenAI–Oracle Stargate sites at Port Washington, Wisconsin (1.3 GW of forecast demand) and Abilene, Texas (1.2 GW), and Meta's Prometheus in Ohio ("1GW+") complete the list in Figure 2.

The numbers are not strictly comparable. Meta reports "compute capacity," Crusoe reports Abilene's "total power capacity," and the Port Washington figure is the local utility's demand forecast rather than the developer's own number. Most of these campuses are still under construction, and Hyperion has no published completion date.

Can a data center use more electricity than a city?

Yes. Running at full power, Hyperion would rank second among the 13 cities in Figure 1, behind only New York City. Amazon's Northern Indiana campus (21.0 TWh) would pass Los Angeles, and Microsoft's Fairwater (17.5 TWh) and the Susquehanna campus (16.8 TWh) would each use more than Austin, Memphis or Philadelphia. Even the smallest campus shown, Meta's 1 GW Prometheus, would use 8.76 TWh at full power, 1.6 times New Orleans's 2025 retail sales and just under Seattle's.

At the state level, Hyperion's full-power total would exceed the 2025 retail electricity sales of 19 states plus the District of Columbia, including Kansas, Nevada, Utah and Connecticut, according to EIA data. It would sit just below Mississippi.

How many homes can 1 gigawatt power?

About 812,000 average U.S. homes for a year, if the gigawatt runs continuously. That figure divides 8.76 TWh by the 10,791 kWh an average U.S. residential customer bought in 2022, the latest year in EIA's published FAQ. By the same math, Hyperion at full power equals about 4.1 million homes. Household use varies widely by state, from 14,774 kWh in Louisiana to 6,178 kWh in Hawaii, so local home counts will differ.

How much of U.S. electricity do data centers use?

U.S. data centers used 192 TWh in 2024, or 4.7% of the country's electricity, according to LBNL's June 2026 update. Its Reference Case projects 464 TWh in 2028 and 649 TWh in 2030, or 11.8% of forecast U.S. use, with a range of 521 to 843 TWh. The 2030 Reference Case is more than Texas, the largest state, sold to all its customers in 2025 (533 TWh).

Grid operators are seeing far more requests than that. ERCOT, which runs most of Texas's grid, was tracking about 474 GW of large loads seeking to connect as of June 2026, roughly 90% of them data centers. LBNL estimates the whole country will need about 148 GW of data center interconnection capacity by 2030, so most of those requests are unlikely to be built.

Methodology & caveats

Every campus energy value in this graphic is derived by hardware.co as planned capacity × 8,760 hours (one year at full power), the same method used by the Visual Capitalist piece that inspired it. Capacity figures come from each developer's own announcement, earnings call or SEC filing, or from the utility serving the site (WEC Energy Group for Port Washington), and they measure different things: compute or IT capacity, total power capacity, contracted supply or forecast grid demand. Meta's Prometheus is shown at 1 GW, though Meta says "1GW+". None of the developers publishes expected annual consumption.

City figures are the best primary numbers available and are not perfectly comparable. New York City is NYISO's Zone J annual energy for 2025, a grid-level load including losses. Philadelphia and Phoenix come from 2022 city greenhouse gas inventories and cover use inside city limits. The other cities are 2025 retail sales of the utility that serves them (from Form EIA-861), and those service territories can extend beyond city limits. The source article's figures for New York City (46.88 TWh) and Madison (2.80 TWh) could not be matched to a primary source and were replaced with the NYISO and EIA values shown.

State values are EIA's final 2025 all-sector retail sales. U.S. totals and projections come from LBNL's 2025 Update, which revised earlier estimates slightly down and excludes cryptocurrency mining. Homes per gigawatt uses EIA's 2022 average residential purchases. Ranks, shares, multiples and the 50%-use scenario are hardware.co calculations. Chart labels are rounded for display; tables and CSV downloads carry the exact values.

Sources

  1. [1]
    Meta. Deepening Our Investment in Richland Parish, Louisiana (Jul 13, 2026): Hyperion expanded "to 5 GW in compute capacity"https://datacenters.atmeta.com/2026/07/deepening-our-investment-in-richland-parish-louisiana/
  2. [2]
    Amazon. Amazon plans $15 billion investment in Northern Indiana data centers (Nov 24, 2025): "2.4 gigawatts of data center capacity"https://www.aboutamazon.com/news/company-news/amazon-15-billion-indiana-data-centers
  3. [3]
    Microsoft. FY2026 Q1 earnings call (Oct 29, 2025): Fairwater in Wisconsin will "scale to two gigawatts alone"https://www.microsoft.com/en-us/investor/events/fy-2026/earnings-fy-2026-q1
  4. [4]
    Talen Energy. Talen Energy expands nuclear energy relationship with Amazon (Form 8-K, Exhibit 99.1, Jun 11, 2025): 1,920 MW through 2042https://www.sec.gov/Archives/edgar/data/1622536/000162828025030559/a20250611pressreleasebusin.htm
  5. [5]
    Vantage Data Centers. Vantage unveils plans for Frontier, a $25B mega campus in Texas (Aug 19, 2025): 1.4GWhttps://www.vantage-dc.com/news/vantage-data-centers-unveils-plans-for-frontier-a-25b-mega-campus-in-texas-to-meet-unprecedented-ai-demand/
  6. [6]
    WEC Energy Group. Investor update, September 2026 (Form 8-K exhibit): 1.3 GW (Vantage, Port Washington) and 2.6 GW (Microsoft) of demand forecast through 2030https://www.sec.gov/Archives/edgar/data/783325/000078332526000099/a092026septemberfinal002.htm
  7. [7]
    Crusoe. Crusoe expands AI data center campus in Abilene to 1.2 gigawatts (Mar 18, 2025)https://www.crusoe.ai/resources/newsroom/crusoe-expands-ai-data-center-campus-in-abilene-to-1-2-gigawatts
  8. [8]
    Meta. Q2 2025 earnings call transcript (Jul 30, 2025): Prometheus "the world's first 1GW+ cluster"; Hyperion "up to 5GW over several years"https://s21.q4cdn.com/399680738/files/doc_financials/2025/q2/META-Q2-2025-Earnings-Call-Transcript.pdf
  9. [9]
    NYISO. 2026 Load & Capacity Data Report (Gold Book), Table I-2: baseline annual energy by zone, 2025 actualhttps://www.nyiso.com/documents/20142/2226333/2026-Gold-Book-Public.pdf
  10. [10]
    City of Philadelphia, Office of Sustainability. 2022 Greenhouse Gas Inventory: "The electricity use in Philadelphia for 2022 was 13,108 GWh"https://www.phila.gov/media/20250326100034/2022-greenhouse-gas-inventory-report.pdf
  11. [11]
    City of Phoenix. 2022 Community Greenhouse Gas Emissions Inventory, Table 4: Scope 2 electricity activity data (GWh)https://www.phoenix.gov/content/dam/phoenix/oepsite/documents/ghg-inventories/final-2022-community-ghg-report-english-08132024.pdf
  12. [12]
    U.S. Energy Information Administration. Annual Electric Power Industry Report, Form EIA-861, 2025: sales to ultimate customers by utility (Sales_Ult_Cust_2025)https://www.eia.gov/electricity/data/eia861/zip/f8612025.zip
  13. [13]
    U.S. Energy Information Administration. How much electricity does an American home use? (FAQ 97): 10,791 kWh per residential customer in 2022https://www.eia.gov/tools/faqs/faq.php?id=97&t=3
  14. [14]
    Lawrence Berkeley National Laboratory. United States Data Center Energy Usage Report: 2025 Update (June 2026)https://eta-publications.lbl.gov/publications/united-states-data-center-energy-2025
  15. [15]
    ERCOT. Assessing the Grid, Texas Senate panel (Jul 29, 2026): large load interconnection requests as of June 2026https://www.ercot.com/files/docs/2026/07/29/ERCOT-Senate-July-29-Panel-1-Assessing-The-Grid.pdf
  16. [16]
    Vantage Data Centers. OpenAI, Oracle and Vantage announce Stargate data center site in Wisconsin: "close to a gigawatt of AI capacity"https://www.vantage-dc.com/news/openai-oracle-and-vantage-data-centers-announce-stargate-data-center-site-in-wisconsin/
  17. [17]
    U.S. Energy Information Administration. Electricity data by state, HS861 2010-: total electric industry retail sales by state, final 2025 (released Oct 7, 2026)https://www.eia.gov/electricity/data/state/xls/861/HS861%202010-.xlsx
  18. [18]
    Talen Energy. Annual Report on Form 10-K for 2025: Susquehanna generating capacity, 2,494 MWhttps://www.sec.gov/Archives/edgar/data/1622536/000162253626000017/tln-20251231.htm